AKDT,  

October 2022

ANC is Hiring: Recruitment is underway for a variety of vital positions that keep our 24/7 operations running smoothly. Positions that are under active recruitment efforts are posted online at www.JoinANC.com or through Local 71 at the following web addresses: local71.com/jobs. Come join the award-winning staff at ANC. Vacancies include:  Maintenance Specialist Electronics (Technician) Journey II Maintenance Specialist Building/Facility/Construction […]

Read More…

September 2022

Airport Recruitment: ANC is on the lookout for a variety of people to join our work family. Positions that are under active recruitment efforts are posted online at www.joinANC.com or through Local 71 at the following web addresses: local71.com/jobs. All positions at ANC contribute to the overall success of operations.  Vacancies include:  Accounting Technician 1 Maintenance Specialist Electronics […]

Read More…

August 2022

*IMPORTANT UPDATE* ANC Infrastructure Construction: The rehabilitation of the terminal loop road required a six-inch elevation of the road under the terminal loop bridge. Signage posted prior to the bridge displays the maximum height a vehicle can be to drive under the bridge (10’ 6”) to make it out the other side unscathed. There have been multiple […]

Read More…

July 2022

ANC Infrastructure Construction: The end is near! The rehabilitation of the terminal loop road is in its home stretch! Taxis and shuttles are back at the commercial loop and only the ride-share app transportation is on the upper level, as usual. Paving is complete and all that is left is lane striping, which is scheduled […]

Read More…

June 2022

ANC Infrastructure Construction: The rehabilitation of the terminal loop road is coming along nicely, and the traffic pattern returns to its usual route the Friday before Memorial Day weekend. Taxis and shuttles will return to the lower commercial curb June 4. Construction on the loop will be ongoing through the summer with intermittent lane closures. […]

Read More…

May 2022

ANC Infrastructure Construction: The most noticeable construction project that continues to impact the public is the rehabilitation of the terminal loop road. We are striving to have the traffic pattern return to its usual route the Friday before Memorial Day weekend; however, construction will be ongoing through the summer. The much-needed upgrades include storm drain […]

Read More…

April 2022

Terminal Loop Road: PLEASE PAY CLOSE ATTENTION TO SIGNAGE AND DRIVE WITH CAUTION! Construction for upgrades to the terminal loop road kicked off. The Terminal Loop Road (lower ramp) will be closed for approximately 60 days, then subjected to intermittent lane closures for the remainder of the summer. Intermittent lane closures will occur on the […]

Read More…

GARAGE UPDATE: The airport parking garage is operating at 50% reduced capacity until October 2023 as maintenance work is completed. Travelers are encouraged to allow extra time when arriving to utilize offsite parking if needed (learn more). Motorists looking for their vehicle moved due to the construction, or any other parking issue, can call Republic Parking at 907-677-1074.